Project progress - December 2024

The major works will be completed by the end of the year with works wrapping up on 23 December. Some works will be carried over to the new year for completion (see key dates).

All roads and footpaths will be reopened for traffic and pedestrians before Christmas with the final layer of footpath on west side to be laid in the new year.

Come on down and check out the progress in person, and support the local businesses - view their summer opening hours here.

Foreshore works - Before/After

 